SCRUM Posts 2
Posted by Justin Bernard on September 17, 2014
(Because the other list so long to scroll down)
SCRUM 9/17
1) What I did yesterday
- cane creek design
- sense/stat support
2) What I have planned for today
- cane creek design
- sense/stat support
3) What I need from another team member/client
- sense enclosure
- stat dev
- possible cane assistance
Comments
Taylor Bernard on September 17, 2014:
SCRUM 9/17
1) What I did yesterday
- callidus kiosk, overlay comm
- sense enclosure design
2) What I have planned for today
- finalize sense enclosure design/materials
- order materials
- solidworks modeling
3) What I need from another team member/client
- sense enclosure ideas/revisions
Justin Bernard on September 18, 2014:
SCRUM 9/18
1) What I did yesterday
- cane creek design
- sense/stat support
2) What I have planned for today
- cane creek design
- sense/stat support
3) What I need from another team member/client
- sense enclosure
- stat dev
- possible cane assistance
Taylor Bernard on September 18, 2014:
SCRUM 9/18
1) What I did yesterday
- sense enclosure design
- callidus kiosk comm
2) What I have planned for today
- sense enclosure design finish
- source printer/top material
3) What I need from another team member/client
- sense enclosure edits when needed
Taylor Bernard on September 19, 2014:
SCRUM 9/19
1) What I did yesterday
- sense enclosure design
2) What I have planned for today
- sense enclosure design finish
- source printer/top material
3) What I need from another team member/client
- sense enclosure edits when neededJustin Bernard on September 19, 2014:
SCRUM 9/19
1) What I did yesterday
- cane creek design
- sense/stat support
2) What I have planned for today
- cane creek design
- sense/stat support
3) What I need from another team member/client
- sense enclosure
- stat dev
- possible cane assistance
Taylor Bernard on September 22, 2014:
SCRUM 9/22
1) What I did yesterday
- sense enclosure design- start pcb fab
2) What I have planned for today
- finish sense enclosure design
- source printer/price
- finalize top design/material + source material
- finish pcb smd part soldering
- displayIt comm3) What I need from another team member/client
- sense top design/material....important.Justin Bernard on September 22, 2014:
SCRUM 9/22
1) What I did yesterday
- cane creek design
- sense/stat support
2) What I have planned for today
- cane creek design
- sense/stat support
3) What I need from another team member/client
- confirm with displayit status of ship, need to see if i need to drive and get it if not in AVL by weeks end.
- sense new pcb photo for blog
- sense enclosure
- stat dev
- possible cane assistance
Taylor Bernard on September 23, 2014:
SCRUM 9/23
1) What I did yesterday
- finish sense enclosure design- sense enclosure printing sourcing
- start pcb fab
2) What I have planned for today
- find enclosure printer
- finalize top design/material + source material
- finish pcb smd part soldering
3) What I need from another team member/client
- sense top design/material....important.Justin Bernard on September 23, 2014:
SCRUM 9/23
1) What I did yesterday
- cane creek design
- cane creek data test/XML send to server/ development
- sense/stat support
2) What I have planned for today
- callidus hardware assembly + check
- cane creek design
- cane creek data test complete
- sense/stat support
3) What I need from another team member/client
- get me tracking for displayit enclosure
- sense new pcb photo for blog
- sense enclosure
- stat dev
- possible cane assistance
Justin Bernard on September 24, 2014:
SCRUM 9/24
1) What I did yesterday
- callidus hardware assembled + checked
- cane creek design
- cane creek data test completed, data export being saved to mysql
- sense/stat support
2) What I have planned for today
- callidus motion complete/review
- cane creek design
- sense/stat support
3) What I need from another team member/client
- sense build
- stat dev
- possible cane assistance
Taylor Bernard on September 24, 2014:
SCRUM 9/24
1) What I did yesterday
- callidus comm
- sense source and buy enclosure
- sense photos
- pcb assembly
- sense top sourcing
2) What I have planned for today
- sense pcb fab until CA business open
- source and buy enclosure top material and cutting service
3) What I need from another team member/client
Justin Bernard on September 25, 2014:
SCRUM 9/25
1) What I did yesterday
- callidus enclosure received
- callidus motion/dev
- scheduling
- sense/stat support
2) What I have planned for today
- callidus motion/dev
- sense/stat support
3) What I need from another team member/client
- sense build
- stat dev
- possible cane/callidus assistance
Taylor Bernard on September 25, 2014:
SCRUM 9/25
1) What I did yesterday
- enclosure top design/comm/order
- pcb smd fab completion
2) What I have planned for today
- should be free'd up for now on sense until next steps come in
let me know what you need
3) What I need from another team member/client
- other projects needs
Justin Bernard on September 26, 2014:
SCRUM 9/25
1) What I did yesterday
- callidus motion/dev
- cane creek planning
- scheduling
- sense/stat support
2) What I have planned for today
- callidus motion/dev
- sense/stat support
3) What I need from another team member/client
- stat dev, first asses direction on basecamp on that same next steps thread
- possible cane/callidus assistance
Taylor Bernard on September 26, 2014:
SCRUM 9/25
1) What I did yesterday
- callidus vector logos
- sense comm
- sense pcb
- stat
2) What I have planned for today
- stat
3) What I need from another team member/client
- enclosure top logo if we want to do it
Justin Bernard on September 29, 2014:
SCRUM 9/29
1) What I did yesterday
- callidus motion/dev
- callidus enclosure assembly
- sense/stat support
2) What I have planned for today
- callidus motion/dev complete
- need to finish callidus enclosure and mail
- sense/stat support
3) What I need from another team member/client
- callidus stand is major shaky. call and we can figure out solution.
- stat dev, notes on where we are at
- cane creek assitance
Taylor Bernard on September 29, 2014:
SCRUM 9/29
1) What I did yesterday
- sense comm
- stat prototyping
2) What I have planned for today
- stat
- sense parts checkup
- possible wiring when enclosure arrives today
3) What I need from another team member/client
- sense laser logo?
Taylor Bernard on September 30, 2014:
SCRUM 9/30
1) What I did yesterday
- callidus
- sense comm
- stat prototyping
2) What I have planned for today
- stat
- sense enclosure wiring
- callidus production
3) What I need from another team member/client
- callidus production orderJustin Bernard on September 30, 2014:
SCRUM 9/30
1) What I did yesterday
- callidus motion/dev reviews/edits
- callidus enclosure assembly/packaging
- sense/stat support
2) What I have planned for today
- callidus motion/dev edits complete
- need to finish callidus enclosure and mail
- sense/stat support
3) What I need from another team member/client
(in this order)
- find fedex last time or departure in AVL for express saver boxes if already have mailing slip
- callidus/litmos prize icon production
- callidus/litmos app icon production
- stat dev, notes on where we are at
- sense assembly
- cane creek assitance
Justin Bernard on October 1, 2014:
SCRUM 10/1
1) What I did yesterday
- callidus motion/dev reviews/edits
- callidus enclosure assembly/packaging
- callidus overlay adhesion
- sense/stat support
2) What I have planned for today
- callidus dev/app packaging complete
- callidus enclosure pack and mail
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat dev, notes on where we are at, now to move forward with some since of eta
- sense assembly
- cane creek assitance
Taylor Bernard on October 1, 2014:
SCRUM 10/1
1) What I did yesterday
- callidus production assets
- sense comm
- stat prototyping/troubleshooting
2) What I have planned for today
- sense wiring
- stat prototyping
- sense final board componet assembly/board fix
3) What I need from another team member/client
(in this order)
-
Justin Bernard on October 2, 2014:
SCRUM 10/2
1) What I did yesterday
- callidus motion/dev reviews/edits
- callidus enclosure/display packaged and mailed
- sense/stat support
2) What I have planned for today
- callidus dev/bugs
- callidus instructions made
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat dev, notes on where we are at, now to move forward with some since of eta
- sense assembly
- cane creek assitance
Taylor Bernard on October 2, 2014:
SCRUM 10/2
1) What I did yesterday
- stat troubleshoot/prototyping
- sense wiring layout
2) What I have planned for today
- stat troubleshoot software side
- sense assembly
3) What I need from another team member/client
(in this order)
- possible coding assistance
Justin Bernard on October 3, 2014:
SCRUM 10/3
1) What I did yesterday
- callidus dev/bugs
- sense/stat support
2) What I have planned for today
- callidus dev/bugs
- callidus instructions made
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 3, 2014:
SCRUM 10/3
1) What I did yesterday
- stat troubleshooting/programming
- sense wiring layout
2) What I have planned for today
- stat hardware testing
- sense wiring layout3) What I need from another team member/client
(in this order)
Justin Bernard on October 6, 2014:
SCRUM 10/6
1) What I did yesterday
- callidus dev/bugs
- callidus instructions made
- sense/stat support
2) What I have planned for today
- callidus dev/bugs
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 6, 2014:
SCRUM 10/6
1) What I did yesterday
- stat hardware wiring, custom vero board small layout2) What I have planned for today
- stat finish hardware wiring/programming
- possible enclosure printing may do this because it will be cheap (sub 15$) and cool. only take me an hr or so to make enclosure in solidworks.3) What I need from another team member/client
(in this order)
- programming testing soon
Taylor Bernard on October 7, 2014:
SCRUM 10/7
1) What I did yesterday
- stat hardware wiring- stat finish board layout
- start solidworks model
2) What I have planned for today
- finish printed enclosure + send off locally
- stat programming
- sense wiring (check on if i have small enough wire size for minimal clutter, may have to go buy a roll from RS
3) What I need from another team member/client
(in this order)
- programming testing soonJustin Bernard on October 7, 2014:
SCRUM 10/7
1) What I did yesterday
- callidus dev/bugs
- callidus hardware troubleshooting
- moog planning/sales
2) What I have planned for today
- callidus dev/bugs
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 8, 2014:
SCRUM 10/8
1) What I did yesterday
- stat enclosure modeling/hardware wiring
- parts comm
2) What I have planned for today
- stat enclosure pickup, testing fitment
- sense wiring
3) What I need from another team member/client
(in this order)
- code assistance
Justin Bernard on October 8, 2014:
SCRUM 10/8
1) What I did yesterday
- callidus dev/bugs, severe contextLoader AIR bug/issue
- callidus sounds input
2) What I have planned for today
- callidus dev/final app packaged
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 9, 2014:
SCRUM 10/9
1) What I did yesterday
- stat enclosure comm/pickup/assembly
- stat board revision with power requirements needed not on tinyduino
- sense wiring pickup
2) What I have planned for today
- stat testing
- sense wiring/enclosure assembly
3) What I need from another team member/client
(in this order)
- code assistanceJustin Bernard on October 9, 2014:
SCRUM 10/9
1) What I did yesterday
- callidus dev/bugs, severe contextLoader AIR bug/issue
- callidus sounds input
2) What I have planned for today
- callidus edits/final app packaged
- cane creek design
- sense/stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Justin Bernard on October 10, 2014:
SCRUM 10/10
1) What I did yesterday
- callidus dev/bugs resolved, final app shipped
- bass law dns/port
2) What I have planned for today
- finish bass law dns updates
- cane creek design
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 10, 2014:
SCRUM 10/10
1) What I did yesterday
- sense enclosure assembly/wiring layout
- sense board error fix
- stat new onboard RTC
2) What I have planned for today
- finish sense enclosure, Ti top will get here this afternoon as well
- stat testing programming?
3) What I need from another team member/client
(in this order)
-stat coding
Justin Bernard on October 13, 2014:
SCRUM 10/13
1) What I did yesterday
- callidus dev/bugs resolved, final app shipped
- cane creek design
2) What I have planned for today
- cane creek design
- possible callidus support, day one of show
- possible stat/sense support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 13, 2014:
SCRUM 10/13
1) What I did yesterday
- sense enclosure finished/assembled
2) What I have planned for today
- sense testing
- stat mods, testing
3) What I need from another team member/client
(in this order)
- next steps
- coding direction
Justin Bernard on October 14, 2014:
SCRUM 10/14
1) What I did yesterday
- callidus onsite troubleshooting/setup for show day1
- cane creek design
2) What I have planned for today
- cane creek design
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 14, 2014:
SCRUM 10/14
1) What I did yesterday
*power out partial day*
- stat hardware testing
2) What I have planned for today
- stat testing/next steps progress
- cc help
- sense next steps
3) What I need from another team member/client
(in this order)
- stat code
Justin Bernard on October 15, 2014:
SCRUM 10/15
1) What I did yesterday
- callidus onsite troubleshooting for show day2
- stat support
- sales
- cane creek design
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 15, 2014:
SCRUM 10/15
1) What I did yesterday
- stat wiring, troubleshooting, coding
2) What I have planned for today
- stat coding, working element
- sense physical enclosure tweak so sits flat
3) What I need from another team member/client
(in this order)
- stat coding
Justin Bernard on October 16, 2014:
SCRUM 10/16
1) What I did yesterday
- stat support
- sales
- cane creek design
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 16, 2014:
SCRUM 10/16
1) What I did yesterday
- stat troubleshooting
- stat setup BTLE + other boards
2) What I have planned for today
- stat testing running sketch
- fix RTC issue
- sense testing
3) What I need from another team member/client
(in this order)
- stat code
- sense code test via elec imp
Justin Bernard on October 20, 2014:
SCRUM 10/20
1) What I did yesterday
- stat support
- sales
- cane creek design
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 20, 2014:
SCRUM 10/20
1) What I did yesterday
- internal AB projects
- sense working
- stat troubleshooting/rtc working
2) What I have planned for today
- finish small AB internal research
- sense finalizing
- stat testing/troubleshooting/code
3) What I need from another team member/client
(in this order)
- sense code
- stat code
- cane creek apple dev infos
Justin Bernard on October 21, 2014:
SCRUM 10/21
1) What I did yesterday
- stat support
- sales
- cane creek design
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 21, 2014:
SCRUM 10/21
1) What I did yesterday
- internal ab tasks
- stat comm
- sense enclosure mod/rewiring
2) What I have planned for today
- sense photos
- stat comm/troubleshooting/coding
- internal ab project comm
3) What I need from another team member/client
(in this order)
- stat coding/next steps
Justin Bernard on October 22, 2014:
SCRUM 10/22
1) What I did yesterday
- sense coding
- cane creek design
2) What I have planned for today
- complete sense coding
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat working
- sense assembly
- cane creek assitance
Taylor Bernard on October 22, 2014:
SCRUM 10/22
1) What I did yesterday
- ios/droid accounts setup
- sense testing
- stat testing
- ab internal
2) What I have planned for today
- ab stamp comm/next steps to complete
- sense finish calibrating
- stat
3) What I need from another team member/client
(in this order)
- stat
Taylor Bernard on October 23, 2014:
SCRUM 10/23
1) What I did yesterday
- sense testing
- stat next steps
- sense photoshoot research
- ab internal
2) What I have planned for today
- stat possible minimize layout pcb
- stat lcd
- sense testing
- sense naming check
3) What I need from another team member/client
(in this order)
Justin Bernard on October 23, 2014:
SCRUM 10/23
1) What I did yesterday
- sense coding
- stat planning
- cane creek design
2) What I have planned for today
- complete sense coding
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat lcd wired/tested
- stat vibration baselines established
- possible cane creek assitance
Taylor Bernard on October 27, 2014:
SCRUM 10/27
1) What I did yesterday
- sense troubleshooting/coding
- stat research
- internal AB
2) What I have planned for today
- sense next steps. possible shipment. next product steps
- stat accelerometer possibilities/research
3) What I need from another team member/client
(in this order)
- sense next step planning
Justin Bernard on October 27, 2014:
SCRUM 10/27
1) What I did yesterday
- sense coding base complete
- stat planning
- cane creek design
- cane creek client design review
2) What I have planned for today
- debug sense code weight variances/spikes
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- find local/tx shoot locations for sense
- ship sense to AVL once hardware 100% verified correct (weight fluctuations fixed)
- stat code samples?
- possible cane creek assitance
Justin Bernard on October 29, 2014:
SCRUM 10/29
1) What I did yesterday
- stat dev
- stat planning
- cane creek design
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- find local/tx shoot locations/options for sense
- stat hardware
- stat non sd memory saving options
Taylor Bernard on October 29, 2014:
SCRUM 10/29
1) What I did yesterday
- sense dev
- stat dev/troubleshoot/programming
- stat next steps
2) What I have planned for today
- sense next steps
- stat making micro sized device/enclosure steps solid progress
- xively comm
3) What I need from another team member/client
(in this order)
- stat code improvement (threshold) + other code example
Taylor Bernard on October 30, 2014:
SCRUM 10/30
1) What I did yesterday
- stat troubleshoot
- stat next steps hardware line up and research
- stat next steps
- xively comm
2) What I have planned for today
- stat micro board options, parts cost and time, potential layout size
- accelerometer voltage to frequency possibility for threshold improvement
3) What I need from another team member/client
(in this order)
- sense status
Justin Bernard on October 30, 2014:
SCRUM 10/30
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- find local/tx shoot locations/options for sense
- stat hardware
- stat non sd memory saving options
Taylor Bernard on October 31, 2014:
SCRUM 10/31
1) What I did yesterday
- stat mini prototype design and research
- xively comm
2) What I have planned for today
- stat hardware designing
3) What I need from another team member/client
(in this order)
- cc sprocket ideas for improvement
Justin Bernard on October 31, 2014:
SCRUM 10/31
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- cc sprocket icon redesign. you should have the psd that has that main nav in place, let me know if not. try desining some sprocket variations, and put in place at scale. its just breaking down a bit due to scale. maybe try some with less cutouts or fewer teeth.
- find local/tx shoot locations/options for sense
- stat hardware
- stat non sd memory saving options
Justin Bernard on November 3, 2014:
SCRUM 11/3
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- cc load screen designs
- find local/tx shoot locations/options for sense
- stat hardware
- stat non sd memory saving options
Taylor Bernard on November 3, 2014:
SCRUM 11/3
1) What I did yesterday
- CC help
- stat design
2) What I have planned for today
- CC design
- stat prototype design
3) What I need from another team member/client
(in this order)
- CC needs
Taylor Bernard on November 4, 2014:
SCRUM 11/4
1) What I did yesterday
- Cane Creek app design assistance
- stat prototyping steps and research
- Romanian guy contact/discussion
2) What I have planned for today
- CC design help
- finish stat prototype steps + fwd to Romanian guy
(soonest he said he can start messing with stuff is Thursday)
3) What I need from another team member/client
(in this order)
- CC needs- sense next steps (xively, investor next steps, ect)
Justin Bernard on November 4, 2014:
SCRUM 11/4
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- stat hardware
- find local/tx shoot locations/options for sense
- stat non sd memory saving options
Justin Bernard on November 5, 2014:
SCRUM 11/5
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- godesign composite/backgrounds
- stat hardware
Taylor Bernard on November 5, 2014:
SCRUM 11/5
1) What I did yesterday
- stat design, prototyping, comm
2) What I have planned for today
- stat Romanian comm, prototype design adjustments
- possible order Dataflash board to test with
- possible reach out to dev to improve accelerometer vibration sensing
3) What I need from another team member/client
(in this order)
- will have stat downtime between design and production prototype stages, need to figure out what to do during those waiting peroids
Justin Bernard on November 6, 2014:
SCRUM 11/6
1) What I did yesterday
- cane creek design
- stat support
2) What I have planned for today
- cane creek design
- stat support
3) What I need from another team member/client
(in this order)
- godesign designs
- stat hardware
Taylor Bernard on November 6, 2014:
SCRUM 11/6
1) What I did yesterday
- go design design, bg comps
- stat comm, design
2) What I have planned for today
- stat comm
- go design production/design
3) What I need from another team member/client
(in this order)
- sense next steps
Taylor Bernard on November 7, 2014:
SCRUM 11/7
1) What I did yesterday
- go design design
- stat comm
- stat part research
2) What I have planned for today
- stat comm
- go design production/design
3) What I need from another team member/client
(in this order)
- sense next steps- buy ram storage to test on stat?
Justin Bernard on November 7, 2014:
SCRUM 11/7
1) What I did yesterday
- cane creek design
- stat support
- sales (moog/kiosks/etc)
2) What I have planned for today
- cane creek design
- more sales
- stat support
3) What I need from another team member/client
(in this order)
- oso twitter setup
- stat hardware
Justin Bernard on November 10, 2014:
SCRUM 11/10
1) What I did yesterday
- cane creek design
- stat support
- sales
2) What I have planned for today
- cane creek design
- sales
- stat support
3) What I need from another team member/client
(in this order)
- stat hardware
- design support
Taylor Bernard on November 10, 2014:
SCRUM 11/10
1) What I did yesterday
- stat design
- stat parts order
- stat comm
- godesign
2) What I have planned for today
- stat comm/revisions
- kiosk booklet printed material
- AB pres deck
- '14 christmas card
3) What I need from another team member/client
(in this order)
- sense next steps
Taylor Bernard on November 11, 2014:
SCRUM 11/11
1) What I did yesterday
- stat design
- stat comm
- ab internal
2) What I have planned for today
- stat comm/revisions
- kiosk booklet printed material
- stat enclosure ideas
- stat Dataflash test sketches
3) What I need from another team member/client
(in this order)
- sense next stepsJustin Bernard on November 11, 2014:
SCRUM 11/11
1) What I did yesterday
- cane creek design
- stat support
- sales
2) What I have planned for today
- cane creek design
- sales
- internal design projects
- stat support
3) What I need from another team member/client
(in this order)
- christmas card research
- booklet cover/inside design
- stat hardware
- design support
Justin Bernard on November 12, 2014:
SCRUM 11/12
1) What I did yesterday
- cane creek design
- sales research
- meetings setup with mission health
- moog estimate started
- internal design projects help
- stat support
2) What I have planned for today
- cane creek design
- sales
- moog estimate complete
- internal design projects help
- stat support
3) What I need from another team member/client
(in this order)
- booklet cover/inside design
- stat hardware
- design support
Taylor Bernard on November 12, 2014:
SCRUM 11/12
1) What I did yesterday
- cane creek design
- moog site breakdown pdf
- stat design
- xmas card research
- booklet research
2) What I have planned for today
- stat design
- stat dataflash hookup/test
- booklet laser cut pricing quotes
3) What I need from another team member/client
(in this order)
- sense next steps
Justin Bernard on November 13, 2014:
SCRUM 11/13
1) What I did yesterday
- cane creek design
- sales research
- moog estimate
- stat support
2) What I have planned for today
- cane creek design
- moog estimate
- meeting with mission hospital marketing
- stat support
3) What I need from another team member/client
(in this order)
- booklet cover pricing?
- mail sense devices (both, and any other interesting to shoot components you may have still)
- stat hardware
- design support
Taylor Bernard on November 13, 2014:
SCRUM 11/13
1) What I did yesterday
- stat design
- stat r/d
- moog deck
- stat support
- sense pack
2) What I have planned for today
- sense mail
- stat design
- stat enclosure ideas
- stat datalfash test
3) What I need from another team member/client
(in this order)
- stat enclosure ideas
Justin Bernard on November 14, 2014:
SCRUM 11/13
1) What I did yesterday
- cane creek design
- sales research
- moog estimate
- stat support
2) What I have planned for today
- cane creek design
- moog estimate
- meeting with mission hospital marketing
- stat support
3) What I need from another team member/client
(in this order)
- booklet cover pricing?
- stat hardware
- design support
Taylor Bernard on November 14, 2014:
SCRUM 11/14
1) What I did yesterday
- stat hardare/comm
- sense packing/shipping
- ab internal
2) What I have planned for today
- ab internal
- booklet research
- stat options
3) What I need from another team member/client
(in this order)
- booklet cover pricing
Taylor Bernard on November 17, 2014:
SCRUM 11/17
1) What I did yesterday
- stat hardare/comm
- ab internal
- AB Booklet
2) What I have planned for today
- ab internal
- AB Booklet designs/pricing
- stat comm
- stat enclosure ideas (BC thread continue talk)
3) What I need from another team member/client
(in this order)
- sense next steps
- stat next steps
Taylor Bernard on November 18, 2014:
SCRUM 11/18
1) What I did yesterday
- stat hardare/comm
- ab internal
- AB Booklet
2) What I have planned for today
- callidus C4D motion test
- AB Booklet designs/pricing
- stat comm
- stat enclosure ideas (BC thread continue talk)
3) What I need from another team member/client
(in this order)
- sense next steps
- stat next stepsTaylor Bernard on November 19, 2014:
SCRUM 11/19
1) What I did yesterday
- stat hardare/comm
- callidus kiosk c4d file build/renders
2) What I have planned for today
- callidus C4D finish render export with free time slots
- AB Booklet designs/pricing
- stat comm
- stat enclosure ideas (BC thread continue talk)
3) What I need from another team member/client
(in this order)
- booklet next steps
- stat pcb options
Taylor Bernard on November 20, 2014:
SCRUM 11/20
1) What I did yesterday
- go design help
- callidus kiosk c4d file build/renders
2) What I have planned for today
- callidus C4D finish final short stitched clip
- AB Booklet designs/pricing
- go design content sections
- stat enclosure ideas (BC thread continue talk)
3) What I need from another team member/client
(in this order)
Justin Bernard on November 20, 2014:
SCRUM 11/20
1) What I did yesterday
- cane creek design
- sales
- moog estimate
- kiosk render support
2) What I have planned for today
- cane creek design
- moog estimate
- godesign design
3) What I need from another team member/client
(in this order)
- godesign design
- booklet cover design layout
- design support
Taylor Bernard on November 21, 2014:
SCRUM 11/21
1) What I did yesterday
- c4d kiosk finish compositing/upload
- internal booklet
- goDesign
- stat dataflash research
2) What I have planned for today
- goDesign help
- booklet ideas
- dataflash working
3) What I need from another team member/client
(in this order)
- input on booklet
- input on goDesign
- possible stat coding help
Taylor Bernard on November 24, 2014:
SCRUM 11/24
1) What I did yesterday
- stat coding/dataflash working sketch
- internal booklet
- goDesign
2) What I have planned for today
- possible stat board revision for lower cost- internal project
- moog/goDesign assistance
3) What I need from another team member/client
(in this order)
Justin Bernard on November 24, 2014:
SCRUM 11/24
1) What I did yesterday
- cane creek design
- godesign design
- sales
- moog estimate
2) What I have planned for today
- cane creek design
- godesign design
3) What I need from another team member/client
(in this order)
- godesign design
- booklet cover design layout
- design support
Justin Bernard on November 28, 2014:
SCRUM 11/28
1) What I did yesterday
- cane creek design
- godesign design
- sales
- level support
2) What I have planned for today
- cane creek design
- godesign design
- sales
- level support
3) What I need from another team member/client
(in this order)
- CCC&D installation concepting
- level 3d renders
- level url ideas/brainstorming
- level 3d model revision (call me for details)
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
Taylor Bernard on November 28, 2014:
SCRUM 11/28
1) What I did yesterday
- level 3d renders
- level logo ideas
- internal AB
2) What I have planned for today
- level logo design/concepts
- level possible microsite naming
- ccc&d ideas
- diy camera slider cost
3) What I need from another team member/client
(in this order)
Justin Bernard on December 1, 2014:
SCRUM 12/1
1) What I did yesterday
- cane creek design
- godesign design
- sales
- level support
2) What I have planned for today
- cane creek design
- godesign design
- sales
- level support
3) What I need from another team member/client
(in this order)
- CCC&D installation concepting
- level 3d model revision (call me for details)
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
- start building/outlining level photoshoot shot list
Taylor Bernard on December 1, 2014:
SCRUM 12/1
1) What I did yesterday
- level model re-draw componet re-layout
- level naming/logo
2) What I have planned for today
- source 3d print cheaper
- diy cineslider resourcing
- level photoshoot needs
- level new product design look
- CCC&D
3) What I need from another team member/client
(in this order)
- different level design ideas, to spice it up for next proto
Justin Bernard on December 2, 2014:
1) What I did yesterday
- cane creek design
- godesign design
- sales
- level support
2) What I have planned for today
- cane creek design
- godesign design
- sales
- level support
3) What I need from another team member/client
(in this order)
- GoDesign all content pulled into psd's, site plus emailed timeline
- CCC&D installation concepting
- level 3d model revision (call me for details)
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
- start building/outlining level photoshoot shot list
Taylor Bernard on December 2, 2014:
1) What I did yesterday
- level prototype enclosure ideas/design
- level hardware config
- level photoshoot ideas
2) What I have planned for today
- goDesign wireframe layout
- goDesign timeline ideas/mockup
- level enclosure progress
3) What I need from another team member/client
(in this order)
- cccd info
- level enclosure idea direction
Justin Bernard on December 3, 2014:
1) What I did yesterday
- cane creek design
- sales
2) What I have planned for today
- cane creek design
- godesign design
- sales
- level support
3) What I need from another team member/client
(in this order)
- CCC&D installation concepting
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
- start building/outlining level photoshoot shot list
Taylor Bernard on December 3, 2014:
1) What I did yesterday
- goDesign content grabs
- cccd research
- level photoshoot research/template
2) What I have planned for today
- level image references for photoshoot
- cccd research
3) What I need from another team member/client
(in this order)
- cccd
Taylor Bernard on December 4, 2014:
1) What I did yesterday
- level V4 model mockup in 3d
- freshInk web fix
- level photoshoot hardware research
- cccd logo
- cccd research
2) What I have planned for today
- cccd installation ideas
- revise level 3d model
- source 3d printer cheaper
- check painting printed parts for nicer look
3) What I need from another team member/client
(in this order)
- cccd bounce physical ideas for installation
Justin Bernard on December 4, 2014:
1) What I did yesterday
- cane creek design
- CCC&D pitch
- level design support
- lotta sales
2) What I have planned for today
- cane creek design
- godesign design
- sales
- level support
3) What I need from another team member/client
(in this order)
- level model complete
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
- start building/outlining level photoshoot shot list
Justin Bernard on December 5, 2014:
1) What I did yesterday
- cane creek design
- CCC&D pitch
- level design support
- sales
2) What I have planned for today
- cane creek design
- moog meeting at 1pm EST
- sales
- level support
3) What I need from another team member/client
(in this order)
- prudential infographic animation flash production
- level model complete
- photoshoot assessment for level kitchen shoot (images on basecamp). dolly, etc, needs additional to what we already have lighting/cam/lens wise.
- start building/outlining level photoshoot shot list
Taylor Bernard on December 8, 2014:
1) What I did yesterday
- prudential production
- prudential web setup
- level photolist
2) What I have planned for today
- godesign
- level photo list needs
- level photo rental requrements
- stat pcb redesign in spare time
3) What I need from another team member/client
(in this order)
- cccd ideas
- level photolist discuss
Justin Bernard on December 8, 2014:
1) What I did yesterday
- cane creek design
- CCC&D sales
- moog meeting setup
- level design support
- sales
2) What I have planned for today
- cane creek design
- sales
3) What I need from another team member/client
(in this order)
- cane production
- level photoshoot list/needs
- godesign page layout if making progress on design
Taylor Bernard on December 9, 2014:
1) What I did yesterday
- cc app production
- level photolist revision
- stat
2) What I have planned for today
- godesign
- level photo list next steps
- cc app possibilities
- stat pcb rework
3) What I need from another team member/client
(in this order)
- cccd ideas
- level photolist discuss
Justin Bernard on December 9, 2014:
1) What I did yesterday
- cane creek design
- sales
2) What I have planned for today
- moog meeting @1pm
- prudential dev provisioning kickoff call @ 4pm
- sales
3) What I need from another team member/client
(in this order)
- godesign production/layout
- level photoshoot list/needs
- stat
Taylor Bernard on December 10, 2014:
1) What I did yesterday
- godesign production
- ab internal xmas card
- stat
2) What I have planned for today
- stat
- godesign help
- cccd
- level next step
3) What I need from another team member/client
(in this order)
- cccd ideas
- level next steps